3 months ago


L&T secured a contract from the Irrigation and Command Area Development Department (ICAD) of Telangana government for an irrigation project valued at closer to Rs.5000 crore. This project entails irrigating a command area of 9.36 lakh acres across Khammam, Kothagudem and Mahabubabad districts. The overall project will involve construction of a 1263 metre long barrage and 65 radial gates with rope drum hoist arrangements. It will also entail construction of 96.4 km of guide bunds on either side of the barrage. The entire project is expected to be completed in 24 months.